The update due to arrive at Stanford rail station has been derailed again
By Nub News Reporter 12th Oct 2026
THURROCK Council's commitment to restart work at Stanford-le-Hope's rail station appears to have fallen behind schedule again.
The saga of the 'regeneration of the station' which began more than ten years ago, in March 2016, is another long-running sore in a litany of badly-managed Thurrock infrastructure projects.
After initial plans were announced under the Labour council leadership of Oliver Gerrish, the project was continued by the following Conservative administration and parts of the station were demolished in 2020.
The council splashed out more than £4million to buy the adjacent Daybreak Windows site which would host the new transport interchange.
But after that, when unanticipated engineering problems began to unfold and the council's finances collapsed, very little in real terms has happened other than demolition of the buildings on the Daybreak site, which is now an overgrown derelict piece of land. Occasionally the council has forked out thousands to keep Japanese Knotweed from running rampant!

Various portfolio holders and council officers have discussed the site, but deadlines and delivery dates have come and gone without any real action.
Thurrock Nub News last sought an update of what was happening in July and the council said: "Henderson & Taylor are appointed to carry out the infrastructure phase of the project. This phase began in November 2025, which included site clearance.
"The design for the infrastructure phase is complete and Henderson & Taylor will commence those works in September to replace the hoarding, carry out works to prepare platform one for the new station building and complete works to platform two to include the installation of a gateline."
None of that has happened. The hoardings remain in place and nothing has been added to Platform Two.
On Thursday, 1 October, Nub News visited the station to see what had happened.
In a video report editor Neil Speight was able to say: "Nothing!" - though he did spot some Network Rail engineers on site. He asked if it was the start of a rebuilt but was told the team were just sorting a blocked culvert up the track.
Nub News went back to Thurrock Council for an update and we were told: "Works are continuing and a full report updating on progress will be given to Cabinet in November."
Given nothing has happened on the site for months, we asked for a definition of 'works are continuing' – but we are still waiting for the answer to the question to pull into our station.
A look back at six years of the Stanford Rail Station saga:-
August 2025: Station work was not approved: https://thurrock.nub.news/news/local-news/stanford-rail-demolition-was-carried-out-without-relevant-approvals-including-from-c2c-says-councillor-267370
May 2025: Council pledges Stanford rail station will be delivered at a much lower cost: https://thurrock.nub.news/news/local-news/council-pledges-stanford-rail-station-will-be-delivered-at-a-much-lower-cost-than-previously-envisaged-259586
February 2025: Clearance work and tidy up at former Daybreak site costs tens of thousands https://thurrock.nub.news/news/local-news/council-spending-tens-of-thousands-to-clear-site-it-bought-for-stanford-station-regeneration-252387
August 2024: MP calls for rail station answers https://thurrock.nub.news/news/local-news/mp-calls-for-answers-to-stanford-rail-station-project-questions-238647
July 2024: 'Sorry over station blunder' https://thurrock.nub.news/news/local-news/leading-council-makes-personal-apologies-to-residents-acknowledging-she-was-one-of-those-who-voted-for-botched-rail-station-project-236105
February 2024: Throwing good money after bad' https://thurrock.nub.news/news/local-news/council-may-have-to-throw-more-millions-in-pursuit-of-stanford-rail-station-220529
February 2024: Car park site that cost millions is effectively worthless: https://thurrock.nub.news/news/local-news/car-park-site-that-cost-millions-is-effectively-worthless-councillors-are-told-and-stanford-station-project-is-on-the-brink-221732
July 2021: Botched plan put on hold: https://thurrock.nub.news/news/local-news/council-puts-transport-interchange-plan-for-stanford-rail-station-on-hold-and-is-attempting-to-get-green-light-for-station-rebuild-on-its-own
February 2021: Council rail station plans mocked: https://thurrock.nub.news/news/local-news/council-left-byrned-as-rail-station-planning-progress-is-put-on-hold-by-unhappy-councillors
February 2021: Cost overrun and more concerns about station plan: https://thurrock.nub.news/news/local-news/will-there-be-housing-on-station-car-park-site-can-a-bus-really-turn-round-here-and-why-can39t-council-give-any-guarantees-that-budget-won39t-be-bust-again
June 2020: Derailed station project is back on track says council director: https://thurrock.nub.news/news/local-news/derailed-station-project-is-back-on-track-says-council-director-in-report-to-council-that-appears-to-rewrite-history-and-glosses-over-increased-costs
June 2020: Council buys Daybreak site to restart station project: https://thurrock.nub.news/news/local-news/council-buy-up-firm39s-land-to-restart-stanford-station-project-and-promise-major-improvement-to-town
January 2020: Mayor discloses site for transport interchange: https://thurrock.nub.news/news/local-news/mayor-reveals-location-of-land-council-wants-to-purchase-for-station-plan
January 2020: Council comes up with plan to save botched rail station improvements 'inside the current budget envelope': https://thurrock.nub.news/news/local-news/council-comes-up-with-plan-to-save-botched-rail-station-improvements-39inside-the-current-budget-envelope39